Step 7:
A remark on Tracking
Project Progress
You have now created a project plan consisting of a task list,
dependencies between the tasks, a resource pool and assignments
of resources to the tasks. So far the project plan is merely an
estimate of how and by whom the work can be carried out.
When the work begins, so does the next phase of project managment:
tracking the progress!
Tracking means recording project details such as who did what
work, when the work was done, and at what cost. These details
are often called 'actuals'. Tracking actuals is essential
to properly managing a project, as opposed to just planning, a project.
Nevertheless, unless a task has been completed to 100%, tracking
work in progress is in many cases a 'best guess' effort and inherently
risky!
Tracking project performance helps you to answer questions such
as:
- Are tasks
starting and finishing as planned, and, if not, what will be the
impact on the project's finishing date?
- Are resources
spending more or less time than planned to complete tasks?
- Are higher-than-anticipated
task cost driving up the overall cost of the project?
MS Project supports several ways to track progress. The
tracking method you choose should depend on the level of detail
or control required by you, your sponsor, and other stakeholders.
Tracking the fine details of the project requires more work from
you and possibly from the resources working on the project.
Levels of tracking:
- Record project
work as scheduled. Works best if everything in the projects
occurs exactly as planned.
- Record each
task's percentage of completion, either at precise values
or at increments such as 25, 50, 70, 75, or 100 percent.
- Record the
actual start, actual finish, actual work,
actual cost, and actual and remaining duration for
each task or assignment.
- Track assignment-level
work by time period. This is the most detailed level of tracking.
Here you record actual work values per day, week or another interval.
In the following exercise you will track the project as scheduled.
If a certain period of time has elapsed and all of tasks have started
and finished as scheduled, you can record this quickly in Project.
In the following exercise we assume that all the project work
has been carried out as planned until the 12th of December 2008.
This is possible in Project, even though we have only mid November
right now. ;-)
Exercise:
- Open the project in the Gantt Chart view.
- On the main menu bar click on Tools and then select Tracking
and then Update Project ...
- In the Update Project dialog box select the
12th December 2008 in the calender box next to 'Update
work as complete through' and then click OK.
What effect does this have on your project plan?
MS Project records the percentage of completion for the
tasks. It also displays that progress by drawing progress bars
in the Gantt bars for those tasks. Furthermore, check marks
appear in the indicator column for tasks that have been completed.
Have a look at the Project Statistics window again. It should
look like the following illustration:
You can see that MS Project displays now the actual
duration, work and cost of the project under the assumption
that the project work has been carried out as planned until the
12th December 2008. Furthermore, it indicates the actual duration,
work and cost as well as the percentage of completion
for the project.
Please, email
me your answers to the following questions:
- What is the
duration of task 7 when you assign Tina Turner after you
have already assigned Mick Jagger? (Step 5)
- What are
the costs for the entire project after you additionally
assigned Tina Turner to task 7? (Step 5)
- What is the
work associated with phase 3 in the project? (Step 6)
- What are
the Total Cost for the task 'Doing Interviews'? (Step 6)
Advanced MS Project Exercise
Download the project plan file for the advanced tutorial
and save it on you local drive or USP stick.
Your opinion is important:
Please, also tell me in your email what you think of this tutorial,
e.g. was it useful, was it easy to use or not, how long did it take
you to complete it, were the instructions clear? Thank you!
The goal of this eLearning tutorial was to give you a deeper
insight into working with MS Project, in particular how to set up
a resource pool and to assign the resources to the tasks.
If you are interested in learning more about MS Project, then have
a look at the resources page of this tutorial.
You have now successfully completed
this tutorial.
Congratulations!
|